The 138-kilovolt transmission line which crosses Jervis Inlet is scheduled for removal, prompting marine traffic closures in the area.
According to a news release from B.C. Hydro, the removal process is set for Oct.14 to 17, with contingency dates set for Oct.18 to 26.
Closures will be in effect from 8 a.m. to 6 p.m. each day while the power line removal is underway, to ensure safety for the public and B.C. Hydro crews
An alternative marine route around Nelson Island will remain open for the duration of the closure, allowing continued access to the wider Jervis Inlet.
B.C. Hydro says measures will be in place to maintain the Saltery Bay–Earls Cove ferry route during the closure.
“B.C. Ferries will reroute sailings around Nelson Island,” the news release reads. “Updated schedules will be posted at bcferries.com, and they will share the information with service notice subscribers once the updated schedule is available.”
In addition to the marine closures, several Sunshine Coast trails will be closed from Sept. 29, 2025, to Jan. 31, 2026, to support tree removal and road construction required for the transmission line removal.
B.C. Hydro says alternate routes will be available via the Saltery Bay Branch 01 Forest Service Road to Rainy Day Lake, as well as the upper trail to Elephant Lake and Lois Lake.