The Canada Energy Regulator is set to begin oral hearings for a Powell River Energy Inc. electricity export application.
Powell River Energy Inc. operates hydroelectric facilities at Powell Lake and Lois Lake in Powell River, B.C.
The company has an agreement with BR Pacific Hydro Power LLC, an affiliate of Powell River Energy Inc. in the United States, to export all the electricity generated at the two power facilities.
Powell River Energy Inc. applied for a 30-year contract-specific electricity export permit on Aug. 15, 2025.
Under the Canada Energy Regulator Act, the Commission of the Canada Energy Regulator must either issue an electricity export permit without holding a public hearing or recommend that the application be designated for a licensing process.
To recommend that an application be designated, the commission must consider the effects of the exportation of electricity on other provinces and fair market access.
The commission recommended that the Governor in Council designate the application for a licensing process.
Export decisions are typically made through a written process that does not include a public hearing.
The regulatory process for the Powell River Energy Inc. application is unique because this is the first time the commission recommended the Governor in Council designate an export application for a licensing procedure, instead of an export permit process.
The oral hearing is scheduled Nov. 16-20, at the Powell River Town Centre Hotel, starting at 9 a.m. each day.
Members of the public are welcome to attend.